Expansion of Existing Water Treatment Plant

  • Expanded from 400 gallons per minute to 2,000 gallons per minute
  • Project cost = $7.0 million
  • Construction started in August 2014
  • Water treatment plant started up on March 19th, 2015
  • Expanded water treatment plant from 27' x 77' to 60' x 107' (4,341 sq. ft. expansion)
  • Pre-cast concrete wall panels
  • New HVAC system, lab area, chlorine, chemical and pump rooms
  • New pressure filter system
    • 55' long and 12' diamete
    • Filtration rate = 1,600 gallons per minute
    • 3 filter and 1 detention cell
    • Fully automated backwash and simulwash processes
    • Removal of iron and maganese

Click to enlarge image