Approval of Phase 5

The last phase of the Stutsman Expansion received final approval at the November 2015 State Water Commission meeting. Plans are to bid this project Spring 2016. It consists of a 100,000-gallon underground storage addition to one of the system's reservoirs, a 500,000-gallon water tower east of Jamestown in the Spiritwood area, additional pipeline, and the addition of 65 users. Phase 5 will be funded with a 71 percent cost-share loan through the State Water Commission, and with loan dollars that have yet to be determined.